    Case study · Manufacturing · Problem Solving & Statistical Investigation

    Second Opinion: Testing a Root-Cause Analysis Against the Data

    A Tier-1 supplier had to answer its customer's root-cause analysis point by point. We tested each point against the production record, process and material.

    Anonymised project. The client, its customer and the product are not named, and the case carries no figures.

    Client
    A Tier-1 supplier
    Its customer
    An OEM
    Also involved
    The Tier-1's material supplier
    Product
    A component with a recurring defect
    Our part
    A second opinion, working in the background

    Situation

    A defect came back on a component after a long run without it. Then it showed up in a large share of daily production.

    The customer wrote its own root-cause analysis and asked the Tier-1 to answer it point by point. The Tier-1 and its material supplier did not agree on where the cause sat.

    How it started

    Before it answered, the Tier-1 asked us for a second opinion. Not a new 8D. A review of the analysis that already existed, tested against the production data.

    A second opinion from the supplier's side can look like an argument to avoid the cost. So every point had to stand on records both sides could check. The Tier-1 kept all communication with its customer and its supplier. We worked in the background.

    What we looked at

    We started by rebuilding the record.

    • The production record for the whole period, part by part, by production date, not by claim date.
    • The onset: the point where the defect started, and what changed at that point.
    • The process settings and the material lots in one model, so each effect was read with the others held steady.
    • Material lots compared within the same weeks, to keep a drift over time out of the comparison.
    • Every point of the customer's analysis, read against that record.

    Work packages

    We tested the customer's analysis against the records the plant already had.

    Rebuild the record

    Owner
    The Tier-1's engineers, with our analyst
    Scope
    One table, part by part, from every production log.
    Closed when
    Every part traces to its date, its settings and its material lot.

    Test the explanations

    Owner
    Our analyst
    Scope
    The process settings and the material lots in one model.
    Closed when
    An effect counts only if it holds with the other factors held steady.

    Review the analysis

    Owner
    Our analyst, with the Tier-1's project lead
    Scope
    A written comment on every point of the customer's analysis.
    Closed when
    Each comment names the record it rests on.

    Agree how to test further

    Owner
    The Tier-1's project lead
    Scope
    No new trial until the plan was agreed.
    Closed when
    Plan, sample size and decision rule agreed in writing before any sampling.

    How the work ran

    Documents first
    Written comments, each tied to the record it rests on.
    Then a call
    Only where a point needed discussion.
    All along
    The Tier-1 spoke to its customer and its supplier. We prepared the evidence.

    What the data showed

    • The process settings had an influence.
    • The largest share of the variation followed the material supplier's lots.
    • The onset lined up with a change in the material, not with a change in the process.

    What the data could not show

    • The exact mechanism. The data showed an association that held with the other factors held steady. It did not prove a single cause.
    • How much the part's own design adds. The analysis kept it as a second factor, not the trigger.

    Outcome

    The Tier-1 answered its customer with this evidence. The customer revised its analysis: one process factor was removed from its conclusions, and the improvement was tied to the material.

    Exit criteria

    • Every point of the customer's analysis had a written answer with its evidence.
    • Any further trial runs on an agreed plan, with the decision rule set before sampling.

    The Tier-1 decided what to send. The customer owned its analysis.

    What stayed with the client

    • The analysis report the Tier-1 used with its customer and its supplier.
    • The rebuilt production record, part by part.
    • A written comment on every point of the customer's analysis.
    • A rule for any further trial: plan, sample size and decision rule agreed in writing before sampling.

    Talk first

    Working through a similar quality issue?

    Tell us what is happening, what your customer requires and what your team has tried. We can review the support needed.